Asbestos removed from a 1950s house before it comes down, with the garage kept for the new house
Example project
- Home
- Deephaven one-story from the 1950s, full basement, detached garage built later
- Original request
- Clear the lot for a new house while the garage stays where it is
- Testing
- An MDH-certified inspector surveys both buildings, from the basement floor of the house to the garage roof
- Found
- Asbestos in the tape and wrap on the basement ducts, the basement floor tile and mastic, and the bathroom sheet vinyl
- Clear
- No asbestos in the plaster, the roofing or anything sampled in the garage
- Timeline
- Survey week; five days of notice; four days of removal; a gap of two days or more; then demolition
- Cost
- $10,000
In this example, a family in Deephaven plans a new house on the lot where their 1950s house now stands. The house comes down, but the detached garage, built years later, stays and will serve the new house.